Scheduling the construction of your home

There are many steps in building a log home. We want to ensure that the home you desire is built to your specifications. Listed below are the steps taken in ensuring customer satisfaction and quality construction, when you choose Monkton Manor Specialties, Inc.

An initial meeting is scheduled to go over different floor plans and personalize your log home design. After an evaluation of your specifications an estimate is made and provided to you at no cost. The log home package is then ordered and initial plans are drawn. After you review the plans and make any changes the final plans are drawn and the construction will begin.

After the planning stages of choosing a style home, the layout of the floor plans, interior decor, and choosing a lot, we will begin construction using the following schedule.

Month 1

Obtain building permits
Do the perk tests (if applicable)
Prepare the site and clear a path for a road or driveway
Drill well (If applicable)
Install electric utilities
Dig the hole for the foundation
Pour the footers to start the foundation

Month 2

Install floor joists and sub flooring
Deliver the log package
Start erecting the log package (Depending on the size of the home this may go into month 3)
Frame interior walls, gable ends and dormers
Install exterior doors and windows

Month 3

Install septic system
VAC, Electrical,  Plumbing, and Insulation rough in/ installation
Have HVAC, Electrical, Plumbing, and Insulation inspected.
Install roof covering (shingles, cedar shakes, metal)
Hang and finish drywall, if applicable
Install wood on interior walls, if applicable
Begin preparation for staining of wood, if applicable and painting.

Month 4

Install interior trim and doors
Paint and/or stain interior
Install kitchen cabinets and vanities
Install exterior trim, siding if needed, and soffit
Install porch ceilings
Stain exterior

Month 5

Install floor coverings
Complete the Plumbing and Electrical installations and have them inspected.
Complete the HVAC installation and have it inspected
Have the driveway and sidewalks completed
Do the landscaping
Have a walk through and final inspection

Month 6

This schedule is a perfect scenario. Since we can not predict the weather and some homes are larger than average,  there may be some delays. We include month six just to compensate for any such delays.