Scheduling the construction of
your home
There are many steps in building a log home. We want to ensure that the home you
desire is built to your specifications. Listed below are the steps taken in
ensuring customer satisfaction and quality construction, when you choose Monkton
Manor Specialties, Inc.
An initial meeting is scheduled to go over different floor plans and
personalize your log home design. After an evaluation of your specifications an
estimate is made and provided to you at no cost. The log home package is then
ordered and initial plans are drawn. After you review the plans and make any
changes the final plans are drawn and the construction will begin.
After the planning stages of choosing a style home, the layout
of the floor plans, interior decor, and choosing a lot, we will begin
construction using the following schedule.
Month 1
Obtain building permits
Do the perk tests (if applicable)
Prepare the site and clear a path for a road or driveway
Drill well (If applicable)
Install electric utilities
Dig the hole for the foundation
Pour the footers to start the foundation
Month 2
Install floor joists and sub flooring
Deliver the log package
Start erecting the log package (Depending on the size of the
home this may go into month 3)
Frame interior walls, gable ends and dormers
Install exterior doors and windows
Month 3
Install septic system
VAC, Electrical, Plumbing, and Insulation rough in/
installation
Have HVAC, Electrical, Plumbing, and Insulation inspected.
Install roof covering (shingles, cedar shakes, metal)
Hang and finish drywall, if applicable
Install wood on interior walls, if applicable
Begin preparation for staining of wood, if applicable and
painting.
Month 4
Install interior trim and doors
Paint and/or stain interior
Install kitchen cabinets and vanities
Install exterior trim, siding if needed, and soffit
Install porch ceilings
Stain exterior
Month 5
Install floor coverings
Complete the Plumbing and Electrical installations and have them
inspected.
Complete the HVAC installation and have it inspected
Have the driveway and sidewalks completed
Do the landscaping
Have a walk through and final inspection
Month 6
This schedule is a perfect scenario. Since we can not predict the weather and
some homes are larger than average, there may be some delays. We include
month six just to compensate for any such delays.
Thank you for your interest.